A developer has demonstrated your application and shared a repository. Before accepting delivery, identify the exact version, rebuild it in an environment you control and run agreed business scenarios. Record the evidence against that version and use it to support the payment decision. Access to source files alone does not establish that you can operate the application, that every dependency is included or that the seller has transferred the necessary intellectual property rights.
Record the repository, branch and commit identifier. The identifier identifies a version, rather than certifying its quality. If a fix changes the source, update the reference and repeat the relevant checks. A screen recording of a live application is weak evidence unless the handover record connects that application to the delivered build. Make the connection through a build log, a version record and reproducible test steps.
Have the developer identify external services, paid dependencies and accounts that remain necessary after delivery. Record who will own and pay for each account. Where a commercial library is involved, request its identity and licensing documents. Being downloadable does not establish that it can be redistributed with your product. Specialist review may be appropriate when the application will be resold or embedded in another offering.
Before the acceptance window starts, obtain an installation guide, tool versions, synthetic test data and a list of known defects. Also agree how test messages and payment events will be isolated from real customers. A test that unexpectedly emails your entire customer base creates a new problem without answering whether delivery meets the specification.
A separate database record could identify an anonymised fixture, its checksum, a restore procedure and a migration log. Keep evidence in a controlled shared location and give each record a stable identifier. A payment instruction can then reference a short set of records rather than an unstructured pile of attachments. Do not put secrets into screenshots intended for a dispute reviewer.
An acceptance clause for discussion could say that release requires completion of listed scenarios on the recorded version, that rejection must identify a reproducible deviation and that scope additions require a separate agreement. The parties still need to settle deadlines, authority and consequences under their contract. An operational checklist does not decide the law that governs the transaction.
If credentials entered the source history, deleting their current line is not a sufficient response. GitHub's guidance prioritises revoking or rotating exposed secrets. For the customer, that translates into issuing replacement credentials and checking that the deployment uses them. Any wider history cleanup should have its own agreed scope and evidence.
Stop final release when a critical module is missing, operation depends on an undisclosed seller-controlled service or testing requires giving the developer unrestricted access to your unrelated production systems. A failed build is not automatically evidence of dishonesty. It can also result from a version mismatch, a missing network permission or an incomplete installation guide. Diagnose the cause before assigning blame.
If the files pass technical tests but rights remain disputed, record technical findings without claiming legal acceptance. If a requested feature was never in the agreed scenarios, negotiate a scope change before testing it as a mandatory condition. If the review deadline approaches, follow the notice mechanism in the contract instead of assuming an informal chat has extended it.
Compare the proposed release sequence with the published outline of transaction stages, then obtain the actual operating terms for your deliverable.